What an interval objective changes

When does the greedy choice stop working?

Interactive example

Five compatible-or-overlapping jobs; filled bars show the best schedule for the selected objectiveAw=2Bw=2Cw=2Dw=10Ew=102468
Earliest finish
4
Best for this objective
4
Optimise

Earliest finish is optimal for this count objective, but the same schedule can lose to a weighted objective.

See the values
Five compatible-or-overlapping jobs; filled bars show the best schedule for the selected objective
JobStartFinishWeight
A022
B242
C462
D0610
E681

What to notice

Compare an earliest-finish schedule with an exhaustive optimum under two objectives.

Conditions

Each job has positive duration and weight; a next job may start at the previous finish time.

What this example cannot show

The exhaustive comparison covers only these five authored jobs and is not a scalable weighted-scheduling algorithm.